[91.13] The NGST Yardstick Integrated Science Instrument Module (ISIM) Feasibility Study

M.A. Greenhouse (NASA GSFC \& NGST Project Office), NGST ISIM Team

The Next Generation Space Telescope (NGST) Integrated Science Instrument Module (ISIM) is a distributed system consisting of a cryogenic instrument module that is integrated with the Optical Telescope Assembly (OTA) and science processors, software, and other electronics located in the Space Support Module (SSM). The ISIM system provides structure, environment, and data handling for several modular science instruments as well as several components of the OTA optics train.

An ISIM baseline design and feasibility study is ongoing at GSFC. This pre-Phase A design was developed for integration with the Yardstick NGST architecture and packaging in a 5 m class EELV fairing. The goals of this study are to: [1] demonstrate mission science feasibility, [2] assess ISIM engineering and cost feasibility, [3] identify ISIM technology challenge areas,and [4] enable smart customer procurement of the NGST. In depth results from this work beyond those displayed here can be found at: http://www701.gsfc.nasa.gov/isim/isim.htm

The flight ISIM will be developed by a GSFC led IPT that includes members from the STScI and, during Phase A/B, will grow to include the NGST Prime Contractor, and science instrument development teams from European, Canadian , and US science communities. Science instruments will be competitively procured from the science community, and will be integrated into the ISIM by GSFC. The flight qualified ISIM will then be delivered by GSFC to the NGST Prime Contractor for observatory level integration.

At the start of NGST Phase A (Spring 1999), two competing prime contractors will begin development of separate NGST architectures, and the ISIM IPT will develop two ISIM designs corresponding to these architectures. Down selection to a single design will occur during mid 2001.

The ISIM team welcomes science community feedback. Contact the IPT lead: Matt Greenhouse: matt@stars.gsfc.nasa.gov.


If the author provided an email address or URL for general inquiries, it is a s follows:
http://www701.gsfc.nasa.gov/isim/isim.htm

matt@stars.gsfc.nasa.gov